Sharp Glazing and Sharp Steel

Hackney warehouse, both divisions

Hackney, E8 · Warehouse conversion, 1920s print works

Demo shot 13 · assets/theta/proj-hackney-hero.jpg

Finished project, exterior, square to the elevation in flat overcast light, the whole of the work visible in one frame with the untouched parts of the building either side of it for comparison.

21:9
Illustrative image

The architect drew steel to the street and courtyard and aluminium to the rear. The client asked whether one company could carry both. The street now keeps its original rhythm in thin steel.

One survey, one schedule and one fitting team covered both divisions: Sharp Steel supplied the street, courtyard and mezzanine, Sharp Glazing the rear doors and the roof. The courtyard screen was craned over the wall on a single road closure, and the roof now brings daylight to the middle of a deep plan.

The work

Photography requiredproj-hackney-the-work-rear-doors-open.jpg

Five-leaf bi-folding door fully stacked to the left, shot from deep inside the living space toward the courtyard at midday, the stack reading as a single thin column.

4:3
Rear doors openIllustrative image
Photography requiredproj-hackney-the-work-courtyard-screen.jpg

Courtyard steel screen from outside at a three-quarter angle after rain, water beading on the glass, wet brick underfoot.

4:3
Courtyard screenIllustrative image
Photography requiredproj-hackney-the-work-rooflights-from-the-deck.jpg

The pair of frameless rooflights seen from the roof deck in low evening sun, the 5 degree fall visible as a shallow slope across both units.

4:3
Rooflights from the deckIllustrative image
Photography requiredproj-hackney-the-work-steel-reveal.jpg

Steel window reveal photographed from inside, the frame set tight against exposed brick with side light grazing the mortar joints.

4:3
Steel revealIllustrative image
Photography requiredproj-hackney-the-work-mezzanine-screen.jpg

Internal steel screen dividing the mezzanine bedroom, shot from the stair landing above and behind so the void drops away below the frame.

4:3
Mezzanine screenIllustrative image
Photography requiredproj-hackney-the-work-crane-day.jpg

Crane lifting the glazed steel screen over the courtyard wall at seven in the morning, street closed, banksman with raised hand in the foreground.

4:3
Crane dayIllustrative image

Installed systems

Street windows, Sharp Steel
Steel windows
Courtyard screen, Sharp Steel
Glazed steel screen
Mezzanine screens, Sharp Steel
Steel internal screens
Rear doors, Sharp Glazing
Bi-folding doors
Rooflights, Sharp Glazing
Frameless rooflights
Project details

At a glance

Programme
8 weeks, survey to install
Completed
June 2026

Constraints

Street elevation must read as steel
The original windows were steel. Planning required the replacements to keep thin frames and the same eight-opening rhythm.
Noise from the bus route
The bedrooms face the street. The specification called for a measured acoustic figure, not a rating band.
Courtyard access
The courtyard is reached only through the building or over a 2.4 m wall. The glazed screen had to be craned in on a single road closure.
Roof structure
The existing roof had a 3 degree fall. Overhead glazing needs 5 degrees minimum, so two zones were reformed before the rooflights were set.
One programme
Steel and glazing had to arrive in a sequence that let the scaffold come down once.

Product schedule, as fitted

Street windows, Sharp Steel
Steel, 8 units, largest 1450 x 2600 mm, triple glazed
Street acoustic
44 dB
Courtyard screen, Sharp Steel
Glazed steel screen, 4200 x 3000 mm overall, 1 door leaf at 1000 x 2600 mm
Mezzanine screens, Sharp Steel
Steel-framed internal, 2 screens, 25 mm sightline, leaf 1000 x 2600 mm, dividing the bedroom from the void
Rear doors, Sharp Glazing
Bi-folding, 5 leaves, 52 mm sightline, leaf 1000 x 2700 mm, opening 5000 mm wide, Uw 1.3, stacks to one side
Rooflights, Sharp Glazing
2 frameless, structural silicone, largest 2500 x 4000 mm, Uw 1.0, 5 degree fall
Finish, external
Bronze anodised to the street and courtyard
Finish, rear and internal
RAL 7021 matt
Security
PAS 24, Secured by Design, at every ground floor opening
Weathertightness
BS 6375; rooflights to BS 5516-2
Guarantee
10 years, both divisions, one document

How it ran

01 · Survey
One visit, both divisions. Street, courtyard, mezzanine, rear and roof measured together. The 3 degree roof fall was recorded as a defect.
02 · Quote
Issued in 3 working days as one schedule with the division named against each line.
03 · Manufacture
Five weeks, steel and glazing running in parallel to one delivery date.
04 · Roof reforming
Two roof zones rebuilt to a 5 degree fall while units were in production. We supplied setting-out drawings and upstand heights.
05 · Crane lift
One Sunday road closure. Courtyard screen in, scaffold adjusted the same day.
06 · Install
Fourteen days by one fitting team. Street windows, then courtyard, then rear doors, then rooflights.
07 · Handover
Every opening cycled, drainage flushed, one guarantee document covering both divisions.

Result

Openings supplied
14, across both divisions
Suppliers the client dealt with
1